2.50 CONTRACTOR PAYMENTS AND PRICE ADJUSTMENTS

2.51 PAYMENT FOR MATERIAL ALLOWANCE

2.52 PAYMENT FOR UNEXPECTED CLASS 12 ROCK EXCAVATION

When Class 12 excavation is unexpectedly encountered and there is no contract item for Class 12, the quantity of Class 12 will be paid for as Extra Work. (Refer to Construction Manual 2.36 for procedure used to process a Change Order.)

Approval for Work

2.53 PRICE ADJUSTMENT GUIDE FOR REASONABLY CLOSE CONFORMING, REASONABLY ACCEPTABLE, AND DEFICIENT WORK

Every effort should be made to prevent substandard work and/or noncomplying material from being incorporated into the project. However, when work and/or materials are deemed to be noncomplying, Specifications 1105 and 1101 give authority to the project engineer for determining if construction work or materials are acceptable and/or within reasonably close conformity to the plans and specifications. Therefore, the project engineer must decide whether deficient work is to be removed and replaced or left in place with a price adjustment. Unusual situations or circumstances may warrant consultation with the Office of Construction and the Office of Materials.

NOTE: A price adjustment is no substitute for specification compliance and "unacceptable work" shall always be removed and replaced with acceptable work. Further, contractors need to be given an option of removing deficient work and replacing with acceptable work in lieu of a price adjustment.

Price adjustments of $100 or less need not be formalized in a change order.

Guide Schedules for Price Adjustments
A. Gradation

B. PCC Slump, Air Content, and Rain Damage

ADJUSTMENT SCHEDULE

C. "L" Joint Tie Steel Deficiencies
Tolerance problems with "L" joint tie steel shall be corrected according to procedures established in Construction Manual 9.26. (Note: "BT" and "KT" deficiencies usually require field correction.)

An adjustment in the contract unit price shall be made for out of tolerance "L" joint tie steel areas. This price adjustment should be a reduction of 5% to the contract unit price per m2 (sq. yd.) for affected areas. It should be applied to a computed effective area bounded by one half the distance to closest adjacent "in tolerance" (in each direction) multiplied by the placement width. This price adjustment is intended not to apply to individual out of tolerance tie steel.

D. Bridge Floor Overlay price adjustments are prescribed in Appendix 2-34(D).

E. Macro texture adjustments will be determined by the project engineer on a case-by-case basis depending on severity and amount of surface area involved.

For texture depth measurement criteria, refer to Construction Manual 9.43. Texture depths less than 1.5 mm (1/16 inch) shall be corrected by sawing in grooving or diamond grinding. Texture depth exceeding 4.5 mm (3/16 inch) may require price adjustment as directed by project engineer. Price adjustments for over depth grooving are found in Appendix 2-34(E).

F. Traffic Control

G. Asphalt

H. Adjustments for Other Contract Administration Issues

I. Steel H-Pile Weight Deficiency

2.54 PRICE ADJUSTMENT CHANGE ORDERS

2.55 FINAL PAYMENT TO CONTRACTOR

2.56 FUEL ADJUSTMENT