I-80/I-380 construction

Construction Updates

Get the most current construction information at 511ia.org.

2018-2019 Construction

Travelers in the area can expect to see preparation work like vegetation clearing, grading along shoulders and utility relocations throughout the project area as we continue to prep for upcoming construction activities throughout the interchange. Construction activities are scheduled to begin in the fall of 2018 and during 2019.

Construction Alert: Kansas Avenue will be temporarily closed beginning Sept. 17, 2018. The closure is anticipated to last two months.


Additional construction activities planned for 2018-2019 include:

  • Grading work on westbound I-80 to northbound I-380 and eastbound I-80 to southbound U.S. 218.
    • Traffic shifts to temporary shoulder pavement during construction
  • Construction on new eastbound I-80 to northbound I-380 bridge.
  • Construction of the relocated Kansas Avenue (2018) and 340th (2019).

Construction will continue on a new interchange at Forevergreen Road. The Forevergreen Interchange is located approximately two miles north of the I-80/I-380 Systems Interchange and two miles south of the existing Penn Street Interchange in North Liberty. Currently, Forevergreen Road is a two lane gravel road that connects the municipalities of North Liberty to the north, Coralville to the south and Tiffin to the west.

If you drive the 80/380 Systems Interchange, follow 511 to get the most current information about closures, lane shifts, and other construction-related impacts.

2018-2019 I-80/I-380 Construction map
View larger map

Project update

As of 9/11/2018

Traffic impacts and potential delays

Systems Interchange construction is scheduled to begin. Traffic impacts and potential delays in the area include:

  • I-80 EB to U.S. 218 SB and I-80 WB to I-380 NB traffic will shift to temporary shoulder pavement during construction.
  • Kansas Avenue continues to be temporarily closed during construction
  • Forevergreen Road Interchange construction continues.
  • All traffic will continue to use existing lanes.

IRXB – INTERREGIONAL EXPRESS BUS SERVICE

Beginning Oct.1, 2018 an IRXB service will be available for commuters traveling to and from their place of work. Buses will run every half-hour between 5:30 a.m. and 8:30 p.m. Buses are ADA compliant and will feature free Wi-Fi. A one-way ticket costs $3.50 and $7.00 for round trip. Commuter parking will be available at IRXB stops.


OVERNIGHT CLOSURES

This fall, it is anticipated that overnight ramp closures will occur. Please follow 511ia.org for the most current construction information and notifications.


Stay connected

Sign up to receive notifications of upcoming events and project updates.