Site Views and Preparation  09-22-2000
Closeup shot of East side of project. Looking West at project overview.
Looking East at the East slope protection silt fence and straw mesh. Pier 3 cofferdam excavation. The contractor is using a sharpened H-pile section to loosen the soil prior to excavation.
Deer on the site on September 19. This photo was taken within 50' of pile driving operations at Pier 2 (during a break in the pile driving). Cutting off piles in Pier 2 footing.
Looking East at project overview. Visitors observing the PDA testing.
Silt collected at the East side silt basin after 0.5 Pier 3 cofferdam excavation. The contractor is using a sharpened H-pile section to loosen the soil prior to excavation.
Looking north along the new access road grading.