Project Description:
This work includes rebuilding the inner portion of the eastbound
Des Moines River Bridge.
Traffic
Impacts :
Two lanes of traffic in each direction in the construction
area will be maintained during peak drive times. Short- and
long-term entrance and exit ramp closures will be required at various
locations along this section.
Project
Schedule: March 2007 - November 2007 |