Keo Way


Project Description:
The Keo Way interchange will be reconstructed. Work will be completed in stages.
Stage 1: Reconstruction work on the north side of I-235 began in Mid Sept. 2004. The exit and entrance ramps in this area are being rebuilt.
Stage 2: Involves grading and building two new bridges over Keo Way for the mainline traffic lanes of I-235.

Project Schedule:
Mid Sept. 2004 - Dec. 2006



Stage 1:
Mid Sept. 2004 - summer 2005 - The westbound exit ramps to Keo Way north and south were reconstructed. A new westbound ramp bridge was built over Keo Way.
Stage 2:
Summer 2005 - Dec. 2006 - The eastbound exit and entrance ramps will be reconstructed. New mainline bridges will also be built in the interchange area.


Traffic Impacts:

Stage 1:
- The westbound exit ramp to Keo Way north was closed. (reopened June 2005)
- The westbound exit loop to Keo Way south was closed.
(reopened June 2005) 
Stage 2:
- Westbound mainline traffic was diverted onto the new ramp lanes and the bridge that was built during Phase 1.
- Eastbound mainline traffic will remain on their existing lanes.
- The eastbound exit to southbound Keo Way closed in June 2005.
- The westbound entrance ramp from 12th St. has closed permanently.

The suggested alternate routes will be the 19th St./MLK Jr. Pkwy, the 6th/7th, and the 2nd/3rd interchanges.

Detour maps:
To Keo Way from I-235
To I-235 from Keo Way

Before and After construction images:
Keo Way before construction
Keo Way after construction

Keo Way map
Keo Way map Keo Way map
Keo Way map Keo Way map
Keo Way map Keo Way map

   

 

Iowa DOT home