8th St. WDM/73rd St. to Cottage Grove Ave.


Note: The mainline paving project has been completed.

Project Description:

The mainline traffic lanes from 8th St./73rd St. to near Cottage Grove Ave. will be rebuilt.
The 28th St. and 35th St. bridges will be reconstructed.
Modifications will be made to the 8th St./73rd St., Walnut Creek and Cummins Parkway bridges.

Project Schedule: March - Dec. 2005
March - summer 2005 - Eastbound traffic will be switched to two lanes in each direction head-to-head on the existing westbound roadway while the eastbound roadway is reconstructed.

  During this shift, the eastbound entrance ramps at 42nd St. and 31st St. will be closed. The eastbound exit ramp at 35th St. will be closed permanently.
Summer - Dec. 2005 - Westbound traffic will be switched to two lanes in each direction head-to-head on the new eastbound roadway while the westbound roadway is reconstructed.

Traffic Impacts:
Two lanes of traffic in each direction on I-235 will be maintained during peak drive times.
Some short term, and some longer term ramp closures will be required during mainline construction.



   

 

 

 