8th St. WDM/73rd St. to Cottage Grove Ave. |
Note: The mainline paving project has been completed.
Project
Description:
The mainline traffic lanes from 8th St./73rd St. to near
Cottage Grove Ave. will be rebuilt.
The
28th St. and 35th St. bridges will be reconstructed.
Modifications
will be made to the 8th St./73rd St., Walnut Creek and
Cummins Parkway bridges.
Project
Schedule: March - Dec. 2005
March - summer 2005 - Eastbound traffic will be switched
to two lanes in each direction head-to-head on the existing
westbound roadway while the eastbound roadway is reconstructed.
| |
During this shift,
the eastbound entrance ramps at 42nd St. and 31st
St. will be closed. The eastbound exit ramp at 35th
St. will be closed permanently. |
Summer - Dec. 2005 - Westbound traffic will be switched
to two lanes in each direction head-to-head on the new
eastbound roadway while the westbound roadway is reconstructed.
Traffic
Impacts:
Two
lanes of traffic in each direction on I-235 will be maintained
during peak drive times.
Some
short term, and some longer term ramp closures will be
required during mainline construction.
|