NOTE: Construction of the bridges is complete and bridges and ramps are now open.
Project
Description: The
interchange will be reconstructed in the following stages:
Stage
1 - A new bridge was built over I-235 for 6th Ave. in
2004.
Stage
2 - New
bridges were built over
I-235 for 7th St. and 5th Ave. in 2005.
Project
Schedule: July 2004 - summer 2005
Traffic
Impacts:
Stage
1 - 7th St. was converted to two-way traffic
across I-235 to maintain north/south traffic while the
6th Ave. bridge was constructed.
Stage
2 - North/south traffic was maintained during this
stage by converting 6th Ave. to two-way traffic while
the 5th Ave. and 7th St. bridges were built.
All ramps are now open.