2004 PROJECTS

 

Mainline paving - WDM

63rd St/IA 28 interchange

42nd St/35th St/ median work

5th/6th/7th interchanges

E. 14th/E. 15th interchanges

E. University bridges/roadway

 

 

 


63rd Street/Iowa 28 Interchange


Project Description:
A new bridge will be built over I-235 and the interchange will be reconstructed. Demolition and construction of the northbound traffic lanes will take place first. The northbound lanes were completed in Nov. and work began on reconstruction of the bridges' southbound lanes.

Project Schedule:
July 2004 - summer 2005
 

Aug. 4 - Nov. 2004 - Traffic will be reduced to one lane in each direction on the west half of the bridge while the east half is rebuilt.
Nov 2004 - summer 2005 - Traffic will be switched to the new lanes and work will begin on the west half of the bridge.

Traffic Impacts:
One lane of traffic in each direction will be maintained on 63rd Street through the construction area.
Some ramp access will be available during various stages of construction. The ramps on the east side of the bridge (WB exit and EB entrance) have been reconstructed, and are now open. The other two ramps (WB entrance and EB exit) are closed and under construction in conjunction with the southbound lanes reconstruction.

63rd St. project map

   

 

 

 

 

 

 