Project
Description: The
interchange will be reconstructed in the following stages:
Stage
1 - The 6th Ave. bridge was completed in December 2004.
Traffic was switched to the new bridge and the 7th St.
bridge was closed for reconstruction.
Stage
2 - New
bridges will be built for 7th St. and 5th Ave. over
I-235.
Project
Schedule: July 2004 - summer 2005
Traffic
Impacts:
North/south traffic will be maintained during Stage
2 by converting the new 6th Ave. bridge to two-way traffic
while the 5th Ave. and 7th St. bridges are being built.
The
westbound entrance ramp to I-235 at 7th St. is closed.
It will remain closed until the bridge is completed.
The
eastbound exit ramp to 7th St. will be closed in winter
2005.
Detour
maps for stage 1:
Suggested
alternate routes from I-235 to downtown.
Suggested
alternate routes to I-235 from downtown.

|