Section 2505. Removal and Construction of Guardrail.

2505.01 DESCRIPTION.
This work shall consist of constructing guardrail by furnishing and installing posts, beams or cables, end anchors, and any special connections and fittings which may be required in the contract documents. It shall also consist of removing existing guardrail.

2505.02 MATERIAL.
The material used for construction of guardrail shall meet requirements of Division 41.

2505.03 REMOVAL AND CONSTRUCTION OF GUARDRAIL.

2505.04 RESERVED.

2505.05 LIMITATIONS.
Attachments to new concrete or to anchor bolts set in epoxy resin shall not be stressed until the new concrete or epoxy resin has attained an age of 3 calendar days. This time requirement may be lengthened by the Engineer during cool weather.

Grading work, if required, shall be completed prior to removal of any existing guardrail or installation of new guardrail.

When a roadway is open to traffic during construction, guardrail installations shall be completed within 5 working days from the day the structure, barrier rail, pavement, shoulder, or whichever is the controlling item of work, is sufficiently completed to allow guardrail installation. In areas where guardrail construction is not restricted by other construction, removal of existing guardrail, if any, and construction of new guardrail, except for end anchors requiring concrete, shall be completed on the same working day. Beam rail shall be fully connected to all posts. Guardrail with end anchors requiring concrete shall be ended with a Type E Terminal Section, a Type II Barricade and a Type A Warning Light, until the final anchor is completed. Concrete for the final end anchor shall be placed no later than the next working day.

When a roadway is closed to public traffic for construction, all guardrail installations shall be completed before opening the road to traffic.

On a roadway that is open to traffic during guardrail construction, each guardrail installation exceeding the 5 working day completion requirement will be subject to a $100 per working day contract price adjustment.

2505.06 METHOD OF MEASUREMENT.

2505.07 BASIS OF PAYMENT.
Payment for guardrail will include the furnishing of all materials, equipment, tools, and labor necessary to complete the removal and installation of the guardrail, including excavation and backfilling. However, excavation in unexpected rock will be paid for as extra work in accordance with Article 1109.03. Unexpected rock will be considered as rock encountered during excavation that was not visible from the roadway and was not indicated in the contract documents. The Engineer may adjust the payment for guardrail in accordance with Article 2505.05.