Section 2301. Portland Cement Concrete Pavement.

2301.01 DESCRIPTION.
Concrete pavement shall consist of a single course of PCC of the type and class specified in the contract. If the class of concrete is not specified, Class C concrete shall be used.

2301.02 TYPE OF PAVEMENT.
Concrete pavement shall be one of two types, Standard or Slip Form.

Irregularly shaped areas of either type of pavement may be formed and finished by hand methods.

When the contract allows standard or slip form pavement, the type is an option of the Contractor. When the contract allows only one type, the type specified shall be used. When the slip form type is specified, small or irregular areas may be constructed with fixed forms.

Reinforced bridge approach sections shall be placed in accordance with the details and limits shown in the contract documents.

2301.03 MATERIALS.
All materials shall meet requirements for the respective items in Division 41. Unless otherwise specified, coarse aggregate shall be of the durability class required by Article 4115.04.

Compatibility of all material combinations shall be the responsibility of the Contractor. If the concrete materials are not producing a workable concrete mixture, a change in the material may be required. Any changes will be at no additional cost to the Contracting Authority.

2301.04 PORTLAND CEMENT CONCRETE PAVEMENT.
Materials for pavement concrete shall be proportioned in any one of the mixtures identified in the current Materials I.M. 529 for the class of concrete specified in the contract documents. Any of the mixtures may be used, at the Contractor's option, provided the gradation of the separate aggregates complies with the gradation required for that mixture. C-5 and C-6 concrete mix proportions will not be used for pavements on Interstate and Primary highways.

After October 31, all items of concrete pavement specified to be constructed with Class B concrete shall be constructed with Class A concrete. The Engineer either will require completion by continuing placement operations past October 31 or will allow the Contractor the option of a winter shutdown. When completion is required, the Contracting Authority will pay the net increase in cost of materials resulting from the change in proportions for any pavement placed within the contract period or authorized extensions thereof, and other increases in cost shall be at the Contractor's expense.

2301.05 EQUIPMENT GENERAL.
The Contractor shall provide sufficient equipment to perform all operations necessary to complete the work. Equipment shall meet the appropriate requirements of Section 2001 and the following provisions.

2301.06 PROPORTIONING AND MIXING EQUIPMENT.
Equipment used for proportioning and mixing concrete materials shall comply with the following:

2301.07 CONSTRUCTION EQUIPMENT FOR PORTLAND CEMENT CONCRETE PAVEMENT.
Equipment necessary for construction of concrete pavement shall comply with the following requirements:

2301.08 BRIDGE APPROACH SECTIONS
Bridge approach sections shall be constructed as shown in the contract documents. All approach pavement reinforcing steel shall be epoxy coated.  Clear distance from face of concrete to near reinforcing steel shall be 2 inches (50mm), unless otherwise noted in the contract documents. The Bridge Approach Section shall be Class C Concrete, with coarse aggregate durability in accordance with Article 4115.04.

2301.09 SETTING OF FORMS.
When fixed side forms are used, they shall be set accurately to the required grade and alignment and shall be founded and secured to maintain that grade and alignment while concrete is being placed and finished and until it is time for the forms to be removed. Forms shall be set on properly compacted materials.

Except as provided below, forms shall be set with the base and top of the form at the respective designed elevations of the subgrade and surface of the pavement at its edge.

With specific approval of the Engineer, forms having a height greater than the designed thickness of the edge of the pavement may be used when set as follows:

After forms are set and locked, they shall be tamped on both sides of each form throughout its entire length with a suitable tool. This tamping shall force suitable material into contact with the base of the form for its entire length and width. Forms that are to support mechanical finishing machines shall be tamped. Tamping of forms set on bases or subbases may be waived if the excavation and bedding of the forms meet the Engineer's approval. Should the earth or subbase supporting the form become softened by rain or standing water so that the form is not adequately supported, the form shall be reset on suitable material before concrete is placed.

Forms shall be cleaned before being reset. They shall be coated with form oil before concrete is placed against them. The oil for this purpose shall produce an oil film on the form that will prevent adherence of concrete to the form.

2301.10 SUBGRADE CONSTRUCTION.
Unless a subbase is specified, the subgrade for standard pavement shall be prepared according to Section 2109.

Subgrade construction for slip form pavement shall be as follows:

The Contractor shall shape and compact the subgrade in accordance with the applicable following method:

The pad line which will support the slip form paving machine and texturing machine shall be constructed substantially to line and grade in a manner so that one of the final operations in its construction will involve cutting in firm, compacted material with a form line excavating machine or other approved equipment. Any subsequent filling in this path may involve wetting and will require thorough consolidation and a recheck for line and grade.

The treatment of subgrade or subbase shall be in accordance with Section 2109.

At the time concrete is placed, adequate provisions shall have been made for drainage away from the area to be paved except on the sides of super elevated curves or in the area of core-outs for bridges or other structures.

2301.11 FIXTURES IN PAVEMENT SURFACE.
All utility accesses, intakes, valve holes, or other fixtures encountered within the area to be paved shall be adjusted to conform to the finished surface of the pavement to be built.

Prior to placement of concrete, the outside of the fixtures shall be cleaned of foreign material for the depth of the concrete.

Fixtures shall be constructed as shown in the contract documents. Fixtures that fall in a form line may be boxed out if a finishing machine is being used. The boxed out concrete shall not be cut or divided on the original form line.

2301.12 PLACING REINFORCEMENT.
Reinforcement shall be installed prior to vibration so as to be in the intended position in the completed pavement. Bars may be supported by approved chairs or may be placed in position by a machine or method subject to approval of the Engineer.

When welded wire fabric reinforcement is used, the concrete shall first be struck off at the elevation specified for the fabric reinforcement, and the sheets of fabric shall be placed as indicated in the contract documents. The sheets of fabric shall be flat, and care shall be used in handling and placing the fabric to ensure its installation in the proper position. The balance of the concrete shall then be deposited and vibrated in a manner to not displace or distort the fabric. Sheets that have become bent or kinked may be rejected.

Alternate methods of placing welded wire fabric reinforcement will be considered for approval.

Load transfer devices may be required in the contract documents. These assemblies shall be accurately placed as shown and shall be securely staked or fastened to the base to line and grade to prevent their movement during subsequent concrete paving operations. Assemblies may be placed in fresh PCC concrete of a Class A subbase, as provided in Article 2114.02, B, to assure a firm connection for the subsequent paving operation. Mechanical dowel bar inserters will not be allowed.

Assemblies that are damaged prior to placement shall not be used. Assemblies damaged after placement shall be replaced prior to paving. Horizontal and vertical alignment of the load transfer bars shall not exceed 1/4 inch (5 mm) from parallel to line and grade. Each assembly shall be placed so the bars are in a horizontal plane at T/2 ± 1/2 inch (15 mm).

The Contractor shall check, with a suitable template or other device approved by the Engineer, the placement of each assembly and the position of the bars within the assembly. If the assembly is found to be placed outside any one of these tolerances, the placement shall be corrected.

Cutting the tie wires of the load transfer assemblies shall be the option of the Contractor.

When dowels or tie bars or other articles are to be anchored in existing concrete, a grout system shall be used as listed in Materials I.M. 491.11 or 491.22 and according to the manufacturer's instructions, subject to the approval of the Engineer.

For horizontal installation of dowels or tie bars, either a pressure injection system with mechanical proportioning and mixing or encapsulated chemical anchors shall be used.

Installation shall be as follows:

Grouting installations utilizing approved encapsulated anchors shall be in accordance with manufacturer's recommendations.

For vertical or angled installations the procedures shall be similar to those for horizontal installation except that pourable grouts may be used. Pourable grouts must be mechanically mixed.

2301.13 PROPORTIONING AND MIXING OF CONCRETE MATERIALS.
The proportioning and mixing materials shall meet the following requirements:

2301.14 PLACING CONCRETE.
The contract documents will show the width in which it is contemplated that the pavement will be constructed, and unless otherwise shown, the pavement shall be constructed in a single pass.

Pavement constructed using ready mixed concrete shall be placed in single lane widths only and in compliance with the following provisions, unless otherwise permitted by the Engineer. Permission will be based on evaluation of type, quality, and quantity of equipment to be used and its anticipated rate of production.

At the Contractor's option, pavements may be placed in single traffic lane widths under the following conditions:

The operation of vibrating units shall be substantially as recommended by the manufacturer and in a manner which complies with the requirements of Article 2301.07, A.

Vertical edges of pavements and backs of curbs shall be cured in accordance with Article 2301.19.

All honeycombed areas on pavement edges shall be satisfactorily repaired immediately after removal of forms.

The Contractor shall backfill behind curbs, as directed by the Engineer, to prevent a flow of water in this area and subsequent undermining of pavement.

2301.15 MULTIPLE LANE CONSTRUCTION.
Unless written approval has been secured for alternate methods described in Article 2301.14, all lanes and sections of pavement shall be constructed to the widths shown in the contract documents.

Expansion and contraction joints shall be constructed to be continuous across all lanes and shall not be staggered.

The edge of the pavement adjacent to the steel form or at any supplemental form or bulkhead that will be abutted by a subsequent slab shall be edged with a tool having a radius of 1/8 inch (3 mm) or less. The cutting edge of the tool moving along the form shall extend downward beyond the rolled edge of the form to its vertical face. The edge on abutting lanes shall be tooled in the same manner.

When keyed joints are required, the keyway shall be fastened to the form by a method that will ensure construction of the keyed joint. These fasteners shall be such that they can remain in place until the concrete has been placed adjacent to and above the keyway.

2301.16 FINISHING AND TEXTURE.
Promptly after the concrete has been placed and consolidated, it shall be finished. Following the finishing operations, texture shall be applied to the surface.

2301.17 INTEGRAL CURB.
When integral curb is required, it shall be constructed preceding the initial set in the concrete, but following the finishing of the main paving slab, except as provided for in Article 2301.18.

Before concrete for the curb is placed, any free water, laitance, dust, leaves, or other foreign matter which may have collected on the edge of the slab shall be removed.

Concrete which has dried, partially hardened, or requires retempering shall not be used.

In placing curb concrete, sufficient consolidation shall be done to secure adequate bond with the paving slab and to eliminate honeycomb in the curb. Care shall be used to avoid disturbing the alignment of forms or the flow line of the gutter.

The final finish on curbs will be secured by hand methods, including use of the 6 foot (1.8 m) straightedge, after removal of the face form or shaping with the curb slip form. The resulting surfaces of both curb and gutter shall be checked by use of the 10 foot (3 m) straightedge and corrected if necessary. In removing face forms, care shall be used to avoid slumps and to avoid disturbance of partially set concrete. The work of constructing integral curb shall proceed as rapidly as finishing operations on the paving slab will permit and in all cases shall be completed in the same working day as the slab is placed, except for the length of section required at the end of the day's run to accommodate the mechanical placing and finishing equipment. In the section left for subsequent placement of curb, the surface of the paving slab along the line of the inside slope of the curb shall be depressed so that the new concrete placed for curb shall be not less than 1 1/2 inches (40 mm) thick. This section of curb shall be tied to the slab by No. 3 (Size 10) hooked steel bars spaced at 1 foot (300 mm) intervals. The surface of the slab back of the key notch shall be roughened, and a depression shall be created around each dowel so that it will project at least 2 inches (50 mm) into the curb concrete.

When curb is built on slabs traversed by headers or contraction or expansion joints, the joints shall be extended through the curb directly over the joint in the slab. All headers and contraction and expansion joints shall be extended through the curb in the same thickness as in the main slab.

All curbs shall be edged, protected, and cured the same as other parts of the paving slab.

2301.18 END OF RUN.
Whenever 30 minutes or more have elapsed since the last concrete has been deposited on the subgrade or if such a delay is anticipated, an approved header shall be installed.

Header joints shall not be constructed within 5 feet (1.5 m) of an intended or previously placed contraction joint. Header joints shall not be constructed opposite a contraction joint in multiple lane construction.

When a header joint is installed, resumption of paving  which abuts the header shall not commence for a minimum of 6 hours.

When delivery of concrete is resumed, it shall be placed adjacent to the exposed face of the header, thoroughly consolidated, and finished with an edging tool at the joint. Sawing and sealing of this joint is not required.

When the end of the day's run occurs in curb section, sufficient curb shall be omitted to accommodate equipment which must be backed out of the way. Construction of the portion of curb omitted shall be as shown in the contract documents and in accordance with Article 2301.17.

2301.19 CURING AND PROTECTION OF PAVEMENT.
After finishing operations have been completed, concrete pavement shall be cured in accordance with Article 2301.19, A.

When an insulation blanket is required, this cover shall consist of a layer of closed cell polystyrene foam protected by at least one layer of plastic film, rated by the manufacturer with an R-value of at least 0.5, or two layers of burlap between 4 mil (100 µm) thick sheets of plastic or an approved alternate.

Placement of the insulating cover may be delayed for up to 4 hours to accommodate initial sawing of joints. The cover may be temporarily removed to perform sawing or sealing. The cover may be permanently removed when the concrete has attained the flexural strength required for opening.

Vertical edges of pavement and backs of curbs shall be cured by the same method used for curing the surface.

Bridge approaches, medians, curbs, widening, and ramps shall be cured in accordance with Article 2301.19, A.

2301.20 SAFETY FENCE FOR PAVEMENT.
In addition to the requirements of Article 1107.09, the Contractor shall install a safety fence for the full width of the slab near the end of each day's run.

This safety fence shall be supported by setting posts near to the edge of the slab. These posts shall extend at least 2 feet (0.6 m) into the ground. Between these posts, a 48 inch (1.2 m) nominal height orange mesh safety fence meeting the requirements of Article 4188.03 shall be stretched and secured to the posts. The twisted ends of the wire shall be cut off flush with the twist so that a tool would be required to cut or otherwise release the fastening.

The fence span between the posts shall be supported with not less than four equally spaced plastic drums weighted to make them stable and difficult to move. These drums shall be as approved in accordance with Materials I.M. 488.02.

On urban work where it is not feasible to set posts, steel drums or sand box supports may be substituted for the end posts.

A similar safety fence shall be placed parallel to and within 50 feet (15 m) from the edge of the slab at all public road and side street intersections. These fences shall be constructed similar to the day's run safety fences.

All safety fences shall be installed within 1 hour of the completion of finishing and curing operations at the fence location to prevent traffic from entering on and damaging the pavement slab. All safety fences shall remain in place and shall be maintained by the Contractor until the concrete has attained the strength and age requirements of Article 2301.31.

Intermediate safety fences may be required for the purpose of opening the slab for access to a side road, side street, or entrance.

2301.21 REMOVAL OF FORMS.
Side forms and curb forms shall be left in place not less than 6 hours after the concrete is placed, unless earlier removal is required by Article 2301.22. Care shall be exercised in removal of forms to prevent cracking, spalling, or over stressing the concrete. All stakes in any form shall be removed before the form is raised. If the method of form removal causes damage to the concrete, the Engineer may require forms to remain in place for more than 6 hours.

2301.22 SAWING JOINTS.
All joints shall be sawed in a single cutting operation for a specific joint substantially true to line to the dimensions shown in the contract documents. Joint sawing shall begin as soon as the concrete has hardened sufficiently to permit sawing without raveling or moving of aggregate.

Joints shall be sawed before uncontrolled cracking takes place. Control joints may be sawed by any saw designed for concrete sawing. If necessary, sawing operations shall be continuous regardless of weather or daylight conditions. Sawing of a joint shall be discontinued if a crack develops ahead of the saw. A heavy span saw, which is supported on the new pavement, will not be allowed for sawing pavements and concrete overlays less than 7 inches (180 mm) in depth.

If the pavement has been covered or protected due to cold weather, rain, or snow, joints shall be sawed by conventional saw equipment only.

Joints requiring compression sealant materials to be installed according to Article 2301.25, shall be sawed so that the compression sealant material can be installed and function correctly.

Should uncontrolled cracking or random transverse cracking occur, the pavement shall be repaired at no additional cost to the Contracting Authority. Repair methods shall be as approved by the Engineer.

When the normal section of pavement is reduced by box-outs such as for intakes, a contraction joint shall be constructed, beginning at one end of the box-out and extending to the pavement edge. This joint shall be constructed by sawing. Alternate types of transverse joints will be considered for approval.

If the length of box-out exceeds 15 feet (4.5 m), a contraction joint shall be constructed at both ends.

2301.23 EXPANSION JOINTS.
Preformed joint material shall be installed perpendicular to the pavement surface. The Contractor shall exercise care throughout the construction of the pavement to ensure that the joint material remains in proper position. The Contractor shall set substantial reference stakes or markers showing the exact location of the joint prior to the placement of concrete adjacent to the joint. After the mechanical finishing equipment has passed over the joint, the joint shall be checked for movement. If movement has occurred in excess of 1/2 inch (10 mm), the installation shall be corrected to its intended position immediately. After the surface finishing has been completed, the joint shall be edged as shown with minimum disturbance to adjacent concrete. Supplemental vibration equipment will be required for proper consolidation of the concrete.

2301.24 RESERVED.

2301.25 SEALING JOINTS.
Unless otherwise provided, before any portion of the pavement is opened to the Contractor's forces or to general traffic, expansion joints and sawed longitudinal and transverse joints shall be sealed with one of the appropriate materials described in Section 4136.

The joint opening shall be sawed or prepared to the designated dimensions and cleaned. The joint shall then be sealed as designated in the contract documents with material meeting requirements of Section 4136.

Joint sealer, in accordance with Article 4136.02, A, shall be used to seal all sawed joints in PCC pavement, shoulders, medians, crossovers, and side road pavements unless otherwise specified in the contract documents.

Within 3 hours after the joint has been wet sawed to the finished dimension, the residue from wet sawing shall be flushed away from the sawed faces by a high pressure water blast, operating with a minimum pressure of 1000 psi (7000 kPa). Within 3 hours after the joint has been dry sawed to the finished dimension, the residue from dry sawing shall be blown from the joint.

Sand cleaning will not be required for joints narrower than 3/8 inch (10 mm), and cleaning of joints shall be as described above. For joints 3/8 inch (10 mm) and wider, sand cleaning shall be used as follows:

When the joint surfaces appear dry by visual examination, the upper 3/4 inch (20 mm) of the joint faces shall be cleaned by sandblast methods, using a mechanical guide, followed by joint cleaning with air blasting. Air compressors shall provide moisture and oil free compressed air. The angle of approach of the sandblast nozzle to each vertical face of the reservoir shall be approximately 30 degrees and the sandblast nozzle must have a guide which inserts in the joint and assures positive location and directional control of the nozzle.

Immediately prior to installation of the backer rod and sealant, the joint shall be cleaned with an air blast. Backer rod will not be required for joints constructed using a shallower depth early, green-concrete saw. When a backer rod is to be installed, the backer rod shall be of the proper size and type and shall be installed dry, with a suitable tool. For transverse joints, the backer rod shall extend to the edge of the pavement.

Joint sealer shall be prepared and installed in the joint and to the proper level as shown in the contract documents and as recommended by the manufacturer. Hot poured sealers shall be heated in a thermostatically controlled heating kettle of a type approved by the Engineer. The material shall be heated to the temperature required for use, but not above that recommended by the manufacturer. When a silicone sealer is installed, the joint faces shall be primed if recommended by the sealer manufacturer. The silicone sealer shall be forced into the joint with a suitable tool as recommended by the manufacturer. Self leveling silicone sealers do not require tooling. After sealing, excess sealer shall be removed from the pavement surface.

Joint sealer shall be placed only when the pavement and ambient air temperatures are 40°F (4°C) or higher. When near this minimum, additional air blasting or drying time or both may be necessary to assure a satisfactory bond to the joint surfaces. When this sealer cannot be properly placed due to late fall work, the Contractor shall submit a joint construction plan and sealing details to the Engineer for approval before paving can begin. The cleaning, sealing, and resawing if required, shall be delayed until the following spring. This delay shall be subject to approval of the Engineer. Joints shall be prepared, cleaned, and sealed after surface correction, if any, or seals damaged from the correction work shall be repaired. When sand cleaning is required, joints shall be sealed the same day they are sand cleaned. Sealing shall be done only when the joint surfaces appear dry by visual examination.

The Engineer may limit the wheel loads and axle loads of equipment operating on the pavement during this operation, if prior to the age and strength specified in Article 2301.31. Additional tests to determine the modulus of rupture may be required.

If early pavement opening is specified, the cleaning, sealing, and resawing, if required, shall be accomplished after the pavement is opened to traffic if hot pour sealing material is used.

The methods of installing preformed elastomeric seals shall be those recommended by the manufacturer and subject to approval by the Engineer. The seal shall be in one piece for the full length of the transverse joint.

2301.26 RESERVED.

2301.27 CONCRETE MEDIAN STRIP.
Where the contract documents call for construction of concrete median strip between adjacent slabs, the Contractor shall construct the median strip to conform to the dimensions shown and to the following provisions:

2301.28 RESERVED.

2301.29 RESTRICTION OF OPERATIONS BECAUSE OF WEATHER.
Concrete shall not be placed when stormy or inclement weather will prevent good quality work. Aggregates containing frozen lumps shall not be used, and concrete shall not be placed on a frozen subgrade. Concrete mixing and placement may be started, if weather conditions are favorable, when the air temperature is at least 34°F (1°C) and rising. At time of placement, concrete must have a temperature of at least 40°F (4°C). Mixing and placing shall stop when the air temperature is 38°F (3°C) or less and falling. During cold weather conditions, concrete less than 36 hours old shall be protected in the manner specified in Article 2301.19, B.

2301.30 NIGHT OPERATION.
Concrete shall not be placed when darkness would prevent good quality work in placing and finishing operations. Unless shown in the contract documents or approved by the Engineer, placing and finishing operations under artificial light will not be permitted, and work shall be organized accordingly.

2301.31 TIME FOR OPENING PAVEMENT FOR USE.
The time for opening pavement for use will be based on the restrictions listed in the table below, with flexural strength determined from beam specimens made during the progress of the work.

Unless otherwise specified in the contract documents, at the Contractor's option, the time for opening pavement may be determined through the use of the maturity method as described in Materials I.M. 383. When the maturity method is used, the time for opening pavement will be based on strength requirements only, as specified in the table above. The Contractor shall furnish all labor, equipment, and materials necessary for the development of the maturity-strength relationship as described in Materials I.M. 383.

Determining that sufficient strength has been achieved for opening a section of pavement shall remain the responsibility of the Engineer when the maturity method is used. The Contractor's maturity testing may be used as the basis for this determination. The Contractor shall provide sufficient documentation of maturity testing before a section may be opened to traffic.

The following shall apply when the maturity method is used:

Personnel performing maturity testing shall be Level I PCC certified technician with training for maturity testing. This certified technician may supervise other persons who may then perform the temperature testing of the constructed pavement.

In cases where early opening of pavement is desirable, the Engineer may require the use of Class M concrete mixtures. Such sections of pavement may be opened to traffic in accordance with the limitations in the above table.

In addition, Class F fly ash and Type IP and Type I(PM) cements shall not be used in Class M concrete mixtures. At the Contractor's option, Class C fly ash may be substituted for up to 10%, by weight (mass), of the cement in Class M concrete mixtures.

2301.32 SHOULDERS.
Shoulders shall be constructed according to Section 2121, 2122, or 2123, as indicated in the contract documents.

2301.33 SURFACING APPROACHES TO INTERSECTING ROADS, DRIVEWAYS, AND TURNOUTS.
Surfacing approaches to intersecting roads, driveways, and turnouts shall be done as provided in Section 2315.

2301.34 METHOD OF MEASUREMENT.

2301.35 BASIS OF PAYMENT.

    A. Portland Cement Concrete Pavement.
    The Contractor will be paid the contract unit price for Standard or Slip-Form Portland Cement Concrete Pavement of the type specified per square yard (square meter) and applies to pavement, concrete pavement widening greater than 6 feet (1.8 m), side street connections, ramps, acceleration and deceleration lanes or auxiliary lanes, and concrete paved shoulders having the same design thickness. Payment for the quantities of pavement in square yards (square meters) will be at a percentage of the contract unit price in accordance with the following schedule:

      Payment Schedule
      Thickness Index Range
      [English (Metric)]
      Percent Payment Thickness Index Range
      [English (Metric)]
      Percent Payment
      0.00 or more
      (0.00 or more)
      103 -0.56 to -0.60
      (-13.98 to -15.24)
      91
      -0.01 to -0.05
      (-0.01 to -1.27)
      102 -0.61 to -0.65
      (-15.25 to -16.51)
      90
      -0.06 to -0.10
      (-1.28 to -2.54)
      101 -0.66 to -0.70
      (-16.52 to -17.78)
      89
      -0.11 to -0.15
      (-2.55 to -3.81)
      100 -0.71 to -0.75
      (-17.79 to -19.05)
      88
      -0.16 to -0.20
      (-3.82 to -5.08)
      99 -0.76 to -0.80
      (-19.06 to -20.32)
      87
      -0.21 to -0.25
      (-5.09 to -6.35)
      98 -0.81 to -0.85
      (-20.33 to -21.59)
      86
      -0.26 to -0.30
      (-6.36 to - 7.62)
      97 -0.86 to -0.90
      (-21.69 to -22.86)
      85
      -0.31 to -0.35
      (-7.63 to -8.89)
      96 -0.91 to -0.95
      (-22.87 to -24.13)
      84
      -0.36 to -0.40
      (-8.90 to -10.16)
      95 -0.96 to -1.00
      (-24.14 to -25.40)
      83
      -0.41 to -0.45
      (-10.17 to -11.43)
      94 -1.01 to -1.05
      (-25.41 to -26.67)
      82
      -0.46 to -0.50
      (-11.44 to -12.70)
      93 -1.06 to -1.10
      (-26.68 to - 27.94)
      81
      -0.51 to -0.55
      (-12.71 to -13.97)
      92 -1.11 or less
      (-27.95 or less)
      80

      Use the following formula to determine the thickness index for the section of pavement thickness:

        TI = (x - S) - T

        Where:

          TI = thickness index for the section

          x= mean core length for the section

          T = design thickness

          S = core length standard deviation (of the sample) for the section.

      The pavement represented by cores deficient from design thickness by 1 inch (25 mm) or greater shall be replaced. The deficient areas and the replacement of the deficient cores will be determined in accordance with Materials I.M. 346.

      At the Contractor's option, cores that are three standard deviations or greater than design thickness may be removed from analysis for thickness index determination. The number of cores removed shall not exceed 10% of the total cores in a section. Cores removed from the analysis shall not be replaced.

      Gaps in the pavement less than 500 feet (150 m), required by staging, will be considered irregular areas for analysis of pavement thickness determinations.

      The percent payment for projects which have all core lengths greater than design thickness will be at least 100%.

    B. Reserved.

    C. Integral Curb.
    Construction of integral curb will not be paid for separately.

    D. Intentionally Left Blank.

    E. Concrete Median.
    The Contractor will be paid the contract unit price for Concrete Median per square yard (square meter).

    F. Bridge Approach Sections.
    The Contractor will be paid the contract unit price for bridge approach pavement per square yard (square meter).  This payment shall be full compensation for excavation for modified subbase and subdrain; furnishing and installing subdrain; furnishing and installing subdrain outlet; furnishing and installing polymer grid; furnishing and placing porous backfill; furnishing and backfilling modified subbase; saw cutting; furnishing and installing reinforcing steel, tie bars, and dowel assemblies; placing, finishing, texturing, grooving, curing, all joint construction; and all other materials and labor to construct the Bridge Approach Section as shown in the contract documents.

    G. Excavation.

      1. When the contract provides a unit price per station (meter) for earth shoulder finishing and the contract also provides a price per cubic yard (cubic meter) for excavation, the Contractor will be paid the contract unit price per cubic yard (cubic meter) for excavation in connection with preparation of subgrade and building of shoulders.

      When the contract provides a unit price for earth shoulder construction, the excavation required for preparation of subgrade and construction of shoulders will not be paid for as a separate item. It shall be considered incidental to construction of pavement and earth shoulder construction and included in those contract prices.

      2. When no price per cubic yard (cubic meter) for excavation is provided in the contract and no unit price is provided for earth shoulder finishing or earth shoulder construction, excavation necessary for preparation for subgrade shall be considered incidental to construction of pavement and included in that contract unit price.

    H. Driveway Surfacing Material.
    For the quantity of driveway surfacing placed, the Contractor will be paid the contract unit price as provided in Section 2315.

    I. Portland Cement Concrete Pavement Samples.
    For furnishing Portland Cement Concrete Pavement Samples of finished pavement or other course according to Article 2301.34, A, or when required in the contract documents, the Contractor will be paid the lump sum contract price. This payment shall be full compensation for furnishing all such samples for all courses or items of work.

    J. RESERVED.

    K. Safety Fence for Pavement.
    The cost of Safety Fence for Pavement shall be incidental to the price for pavement.

Deduction will not be made from the area of pavement for fixtures with an area less than 9 square feet (1 m2). When the adjustment of a fixture to the finished grade line involves a change in elevation of 1 foot (0.3 m) or less, this adjustment shall be made without extra compensation. When this adjustment involves a change in elevation more than 1 foot (0.3 m), this work shall be paid for as extra work, as provided in Article 1109.03, B.

When any of the types of additional protection described in Article 2301.19, B, is necessary, additional payment will be made as extra work at the rate of $1.00 per square yard ($1.20 per square meter) of surface protected. Payment will be limited to protection necessary within the contract period. Protection necessary after November 15 will be paid for only when the work is authorized by the Engineer.

The Contractor shall furnish concrete for test specimens and shall transport the specimens and molds between the grade and plant as directed by the Engineer, without additional compensation.

The above prices shall be full compensation for furnishing all tools, equipment, labor, and materials necessary for construction of the pavement in accordance with the contract documents.

The cost of furnishing, installing, and monitoring vibrators; and vibrator monitoring device, shall be considered incidental to the contract unit price for PCC pavement.