Section 2104.  Channel Excavation

 

2104.01     Description.

Excavate channels or remove and place material involved in channel changes, or similar excavation not normal to Class 10, Class 12, or Class 13 excavation.

 

2104.02     Materials.

Specified in the contract documents or designated by the Engineer.

 

2104.03     Construction.

 

A.    Excavate channels or remove and place material involved in channel changes, or similar excavation not normal to Class 10, Class 12, or Class 13 excavation, as shown in the contract documents. Place this material as shown in the contract documents or as directed by the Engineer.

 

B.    Channel excavation is classified as follows:

 

1.     Class 10 Channel Excavation: refer to Article 2102.03, B, 1.

 

2.     Class 12 Channel Excavation: refer to Article 2102.03, B, 2.

 

3.     Class 13 Channel Excavation: refer to Article 2102.03, B, 3.

 

2104.04     Method of Measurement.

Measurement for Class 10, Class 12, and Class 13 Channel Excavation will be the number of cubic yards (cubic meters) determined as prescribed in Article 2102.04.

 

2104.05     Basis Of Payment.

 

A.    Payment for Class 10, Class 12, and Class 13 Channel Excavation will be the contract unit price per cubic yard (cubic meter).

 

B.    Payment is full compensation for excavating and placement of the material within the free haul limit of 1000 feet (300 m), and for furnishing all equipment, tools, labor, and incidentals necessary to complete the work.